QA002 : The optimum time (O), most likely time ( M), pessimistic time ( P - in days ) _________
Solution :   The expected completion time is calculated by _                                           Now,   E-F-G-H-I  is the critical path here. Now,  Calculate the expected time for each activity  For,                             E-F   expected Time                                                             Simillarly,               for F-G, expected time = 8.16                                      f or G-H, expected time = 7.16         ...