QA002 : The optimum time (O), most likely time ( M), pessimistic time ( P - in days ) _________
Now, E-F-G-H-I is the critical path here.
Now, Calculate the expected time for each activity
For, E-F expected Time
Simillarly, for F-G, expected time = 8.16
for G-H, expected time = 7.16
for H-I, expected time = 12.16
Hence, expected completion time for the project = sum of all expected duration of activities.
= 10.33+8.16+7.16+12.16
= 37.81 Days